
A recent opinion from the Fourth Circuit Court of Appeals[1] highlighted a seemingly minor issue that can have huge future consequences: how to determine pre- or post-award interest on amounts that depend on contingent events in arbitration proceedings. From 2007 to 2008, a series of disputes arose between Kellogg, Brown & Root (“KBR”) and its subcontractor First Kuwaiti General Trading and Marketing Co. (“FKTC”) arising out of the Iraq War (which began in March 2003).
Background
These disputes involved multiple subcontracts and purchase orders with various dispute resolution rules, i.e., ICC, LCIA, ICDR. Consequently, the parties entered into a consolidated arbitration agreement (“Arbitration Agreement”), which set forth a process for resolving multiple disputes in a single ICDR arbitration before the same arbitral tribunal (the “Tribunal”). One of the key issues faced by the parties involved threatened litigation from the United States Government (“USG” or “Client”) against its Prime Contractor KBR relating to several of its subcontracts with FKTC.
In this connection, the parties entered into stipulations/contingent settlements (“Stipulations/Contingent Settlements”) that provided that certain funds were not disputed subject to the resolution of claims asserted or threatened by the USG against KBR. The parties were aware of these contingent claims at the time they entered into the Stipulations/Contingent Settlements but did not know when such claims would be resolved. Those contingent claims were eventually resolved when one dispute between KBR and the USG concluded at the end of 2020 and another dispute concluded in June 2022.
Claim for Interest
At various times during the arbitration, FKTC sought to undo the Arbitration Agreement by asking for a release of the funds referenced in the Stipulations/Contingent Settlements and sought awards of interest on such funds. The Stipulations did not contain any mention of the issue of pre-award or post-award interest.
During the arbitration and in subsequent court proceedings, FKTC took the position that the Stipulations/Contingent Settlements were essentially an “agreed judgment” or a “settlement agreement.” Regardless of the characterization, KBR’s position was that the Stipulations/Contingent Settlements did not contain any reference to interest.
Result
KBR prevailed on its primary counterclaim in the final arbitration award and FKTC sought to recover interest on these Stipulations/Contingent Settlements because it alleged a loss of use of those funds from 2009 to 2022. Both the Tribunal and the Courts concluded that such interest could not be added later to a final award/final judgment. The amount of claimed interest on the Stipulations/Contingent Settlements exceeded $28 million.
While arbitrators generally have latitude in decisions on pre-award interest rates applied to awards, certain states have extremely high statutory rates. For example, practitioners in international arbitrations with an arbitral seat in New York have sought interest at a statutory rate that exceeds 9%. In this situation, the calculation of the amount of interest on an arbitration award can be even more significant than rates typically applied to judgments in Federal courts.
Lesson Learned
The key lesson here is to address the issue of interest on arbitration awards in the arbitration agreement, a procedural order, or in the Stipulations/Contingent Settlements themselves. This is especially true in situations with potentially long dormant periods while awaiting future, contingent events in a forum with high potential rates of interest.
[1] First Kuwaiti Gen. Trading & Contracting W.L.L. v. Kellogg Brown & Root Int'l, Inc., 141 F.4th 522 (4th Cir. 2025)
PartnerNick Simms focuses on international arbitrations and disputes, construction disputes, and civil litigation, including commercial lawsuits, construction litigation involving private and governmental entities, gas ...
Recent Posts
- Should I File My Next Construction Case in the New Texas Business Court? Maybe. (Nov 2025 Update)
- You Agreed to Arbitrate, but the Other Side Refuses, What Now?
- Lesson Learned from a Forever Arbitration – Interest on Stipulated/Contingent Settlements
- Contingent Payment Clause Held Unenforceable due to Unfairness
- Design-Build v. Design-Bid-Build: Legal Considerations
- Texas House Bill 40 Will Reshape the New Texas Business Courts
- Construction Law Update from the 89th Texas Legislature Regular Session
- How do you solve a problem like a tariff? Understanding and addressing tariff risks in construction contracts.
- Should I File My Next Construction Case in the New Texas Business Court? Maybe.
- How Long Does that “One Year Warranty” Last? Longer than You Might Think
TopicsSelect Category
ArchivesSelect Month
- November 2025
- October 2025
- September 2025
- July 2025
- June 2025
- May 2025
- April 2025
- February 2025
- January 2025
- December 2024
- October 2024
- August 2024
- July 2024
- March 2024
- February 2024
- November 2023
- September 2023
- June 2023
- May 2023
- April 2023
- March 2023
- February 2023
- January 2023
- October 2022
- September 2022
- June 2022
- May 2022
- April 2022
- March 2022
- November 2021
- August 2021
- July 2021
- June 2021
- May 2021
- March 2021
- February 2021
- January 2021
- August 2020
- June 2020
- May 2020
- March 2020
- January 2020
- December 2019
- October 2019
- May 2019
- April 2019
- March 2019
- February 2019
- January 2019
- November 2018
- September 2018
- August 2018
- June 2018
- May 2018




RSS Feed
Follow us on X
Follow us on LinkedIn